PRINCE2-FOUNDATION · Question #175
In which lower level process of Controlling a Stage is a Stage Plan updated with actuals?
The correct answer is A. Assessing Progress. See the full explanation below for the reasoning.
Question
In which lower level process of Controlling a Stage is a Stage Plan updated with actuals?
Options
- AAssessing Progress
- BReviewing Stage Status
- CPlanning a Stage
- DReporting Highlights
How the community answered
(24 responses)- A75% (18)
- B4% (1)
- C8% (2)
- D13% (3)