PRINCE2-FOUNDATION · Question #172

The Product-based Planning technique is recommended for which plans?

The correct answer is C. All levels of plan. See the full explanation below for the reasoning.

Question

The Product-based Planning technique is recommended for which plans?

Options

  • AStage Plans only
  • BProject and Stage Plans only
  • CAll levels of plan
  • DAll levels of plan except the Exception Plan