What is the first task in product-based planning?

The correct answer is B. Creating a Product Description for the final product. See the full explanation below for the reasoning.

Question

What is the first task in product-based planning?

Options

  • ACreating a Product Checklist
  • BCreating a Product Description for the final product
  • CCreating a Product Flow Diagram
  • DCreating a Product Breakdown Structure

How the community answered

(68 responses)
  • A
    4% (3)
  • B
    72% (49)
  • C
    16% (11)
  • D
    7% (5)