If a product is to be changed, what else must also pass through change control?
The correct answer is C. Product Description. See the full explanation below for the reasoning.
Question
If a product is to be changed, what else must also pass through change control?
Options
- AStage Quality Plan
- BProduct Breakdown Structure
- CProduct Description
- DQuality Log
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C74% (23)
- D16% (5)