If a product is to be changed, what else must also pass through change control?

The correct answer is C. Product Description. See the full explanation below for the reasoning.

Question

If a product is to be changed, what else must also pass through change control?

Options

  • AStage Quality Plan
  • BProduct Breakdown Structure
  • CProduct Description
  • DQuality Log

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    74% (23)
  • D
    16% (5)