Which of these items does NOT involve the Project Board?

The correct answer is D. Work Package Authorisation. See the full explanation below for the reasoning.

Question

Which of these items does NOT involve the Project Board?

Options

  • AException Assessment
  • BHighlight Reports
  • CProject Closure
  • DWork Package Authorisation

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    13% (3)
  • D
    78% (18)