What provision in Planning can be made for implementing Requests for Change?
The correct answer is C. A Change Budget. See the full explanation below for the reasoning.
Question
What provision in Planning can be made for implementing Requests for Change?
Options
- AProject and stage tolerances
- BContingency plans
- CA Change Budget
- DAdding a contingency margin to estimates
How the community answered
(37 responses)- A11% (4)
- B3% (1)
- C81% (30)
- D5% (2)