If Project tolerances were threateneD) who needs to be notified?
The correct answer is C. Corporate or Programmer Management. See the full explanation below for the reasoning.
Question
If Project tolerances were threateneD) who needs to be notified?
Options
- AProject Board
- BProject Manager
- CCorporate or Programmer Management
- DExecutive
How the community answered
(27 responses)- A11% (3)
- B7% (2)
- C78% (21)
- D4% (1)