The Manage by Exception principle sets tolerances for six areas of the project, Time, Cost and Qualities are three of them, what are the other three?

The correct answer is D. Scope, Risk. Benefit. See the full explanation below for the reasoning.

Question

The Manage by Exception principle sets tolerances for six areas of the project, Time, Cost and Qualities are three of them, what are the other three?

Options

  • AScope, People & Resources, Benefit
  • BScope, Risk, Product
  • CRisk, Benefit, Product
  • DScope, Risk. Benefit

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    9% (3)
  • C
    6% (2)
  • D
    71% (24)