PRINCE2 lists a number of reasons why it is seldom desirable or possible to plan an entire project in detail at the start. Which of these is NOT one of these reasons?
Options
- AA changing or uncertain environment
- BA PRINCE2 requirement
- CDifficulty in predicting business conditions in the future
- DDifficulty in predicting resource availability well into the future