PRINCE2 lists a number of reasons why it is seldom desirable or possible to plan an entire project in detail at the start. Which of these is NOT one of these reasons?

The correct answer is B. A PRINCE2 requirement. See the full explanation below for the reasoning.

Question

PRINCE2 lists a number of reasons why it is seldom desirable or possible to plan an entire project in detail at the start. Which of these is NOT one of these reasons?

Options

  • AA changing or uncertain environment
  • BA PRINCE2 requirement
  • CDifficulty in predicting business conditions in the future
  • DDifficulty in predicting resource availability well into the future

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    81% (29)
  • C
    11% (4)
  • D
    6% (2)