PRINCE2-FOUNDATION · Question #121
Who sets the tolerances for a work package?
The correct answer is B. The project manager. See the full explanation below for the reasoning.
Question
Who sets the tolerances for a work package?
Options
- AThe project board
- BThe project manager
- CThe team manager
- DCorporate or programme management
How the community answered
(58 responses)- A5% (3)
- B72% (42)
- C14% (8)
- D9% (5)