Who sets the tolerances for a work package?

The correct answer is B. The project manager. See the full explanation below for the reasoning.

Question

Who sets the tolerances for a work package?

Options

  • AThe project board
  • BThe project manager
  • CThe team manager
  • DCorporate or programme management

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    72% (42)
  • C
    14% (8)
  • D
    9% (5)