nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #121

PRINCE2-FOUNDATION Question #121: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #121. The question stem and answer options stay visible for context.

Question

Who sets the tolerances for a work package?

Options

  • AThe project board
  • BThe project manager
  • CThe team manager
  • DCorporate or programme management

Unlock PRINCE2-FOUNDATION to see the answer

You've previewed enough free PRINCE2-FOUNDATION questions. Unlock PRINCE2-FOUNDATION for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PRINCE2-FOUNDATION Practice