PeopleCert
PRINCE2-FOUNDATION · Question #110
Which of the following activties is NOT an action of preparing for planned closure?
The correct answer is B. Update the Project Management Team. See the full explanation below for the reasoning.
Question
Which of the following activties is NOT an action of preparing for planned closure?
Options
- AUpdate the project plan wth actua
- BUpdate the Project Management Team
- CRequest a product status account
- DConfirm project has dehvered what defned ii Project PrOduCt Descrtion
How the community answered
(21 responses)- A5% (1)
- B81% (17)
- C10% (2)
- D5% (1)
Community Discussion
No community discussion yet for this question.