PRINCE2-FOUNDATION · Question #107
Whicti of the following management products is NOT updated as part of Managing a stage boundary? 1 Business Case 2 Benefits Review Plan 3 Configuration Item Records 4 Project Brief
The correct answer is A. 1 2 3. See the full explanation below for the reasoning.
Question
Whicti of the following management products is NOT updated as part of Managing a stage boundary? 1 Business Case 2 Benefits Review Plan 3 Configuration Item Records 4 Project Brief
Options
- A1 2 3
- B1 3 4
- C1 2 4
- D23 4
How the community answered
(25 responses)- A84% (21)
- B4% (1)
- C8% (2)
- D4% (1)