PRINCE2-FOUNDATION · Question #107

Whicti of the following management products is NOT updated as part of Managing a stage boundary? 1 Business Case 2 Benefits Review Plan 3 Configuration Item Records 4 Project Brief

The correct answer is A. 1 2 3. See the full explanation below for the reasoning.

Question

Whicti of the following management products is NOT updated as part of Managing a stage boundary? 1 Business Case 2 Benefits Review Plan 3 Configuration Item Records 4 Project Brief

Options

  • A1 2 3
  • B1 3 4
  • C1 2 4
  • D23 4

How the community answered

(25 responses)
  • A
    84% (21)
  • B
    4% (1)
  • C
    8% (2)
  • D
    4% (1)