PRINCE2-FOUNDATION · Question #1056

Which process provides information for the project board to review an updated project plan?

The correct answer is C. Directing a project. See the full explanation below for the reasoning.

Question

Which process provides information for the project board to review an updated project plan?

Options

  • AInitiating a project
  • BControlling a stage
  • CDirecting a project
  • DManaging a stage boundary

How the community answered

(52 responses)
  • A
    4% (2)
  • B
    15% (8)
  • C
    71% (37)
  • D
    10% (5)