During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
The correct answer is B. Checkpont Report. See the full explanation below for the reasoning.
Question
During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
Options
- AHighhght report
- BCheckpont Report
- CIssue Report
- DEnd Stage Report
How the community answered
(26 responses)- A15% (4)
- B73% (19)
- C8% (2)
- D4% (1)