PeopleCert
PRINCE2-FOUNDATION · Question #1031
PRINCE2-FOUNDATION Question #1031: Real Exam Question with Answer & Explanation
The correct answer is B. Project board. See the full explanation below for the reasoning.
Question
During the `initiating a project' process, who specifies the required level of management control?
Options
- ACorporate, programme management or customer
- BProject board
- CProject manager
- DProject assurance
Community Discussion
No community discussion yet for this question.