nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #1031

PRINCE2-FOUNDATION Question #1031: Real Exam Question with Answer & Explanation

The correct answer is B. Project board. See the full explanation below for the reasoning.

Question

During the `initiating a project' process, who specifies the required level of management control?

Options

  • ACorporate, programme management or customer
  • BProject board
  • CProject manager
  • DProject assurance

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice