PRINCE2-FOUNDATION · Question #1031
During the `initiating a project' process, who specifies the required level of management control?
The correct answer is B. Project board. See the full explanation below for the reasoning.
Question
During the `initiating a project' process, who specifies the required level of management control?
Options
- ACorporate, programme management or customer
- BProject board
- CProject manager
- DProject assurance
How the community answered
(61 responses)- A10% (6)
- B70% (43)
- C16% (10)
- D3% (2)