PRINCE2-FOUNDATION · Question #1023
What must be done for a project to be a PRINCE2 project?
The correct answer is A. The project must form part of a programme or portfolio. See the full explanation below for the reasoning.
Question
What must be done for a project to be a PRINCE2 project?
Options
- AThe project must form part of a programme or portfolio
- BThe project must meet the minimum requirements for applying the themes
- CThe project must use the recommended approach to planning
- DThe project roles must be combined wherever possible
How the community answered
(36 responses)- A83% (30)
- B8% (3)
- C6% (2)
- D3% (1)