nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #1023

PRINCE2-FOUNDATION Question #1023: Real Exam Question with Answer & Explanation

The correct answer is A. The project must form part of a programme or portfolio. See the full explanation below for the reasoning.

Question

What must be done for a project to be a PRINCE2 project?

Options

  • AThe project must form part of a programme or portfolio
  • BThe project must meet the minimum requirements for applying the themes
  • CThe project must use the recommended approach to planning
  • DThe project roles must be combined wherever possible

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice