PRINCE2-FOUNDATION · Question #1021

PRINCE2-FOUNDATION Question #1021: Real Exam Question with Answer & Explanation

The correct answer is C. The project board roles defined in PRINCE2 must be used, but other roles can be defined as. See the full explanation below for the reasoning.

Question

Which statement about project roles is CORRECT?

Options

  • AThe project organization must be defined using the roles and responsibilities in PRINCE2
  • BThe project team structure defined in PRINCE2 must be used, but other roles may be added
  • CThe project board roles defined in PRINCE2 must be used, but other roles can be defined as
  • DAny role can be defined as required the responsibilities defined in PRINCE2 are fulfilled