Which management product do the Project Board use to decide whether to authonse initiation?
The correct answer is A. Project Bnef. See the full explanation below for the reasoning.
Question
Which management product do the Project Board use to decide whether to authonse initiation?
Options
- AProject Bnef
- BBusness Case
- CProject Intiation Documentation
- DProject Product Descrption
How the community answered
(20 responses)- A85% (17)
- B5% (1)
- C10% (2)