PeopleCert
PRINCE2-FOUNDATION · Question #1007
What should the benefits management approach define?
The correct answer is C. How the project has progressed against its plans. See the full explanation below for the reasoning.
Question
What should the benefits management approach define?
Options
- AWhat actions will be taken to ensure the project's outcomes are achieved
- BWhat will be used to record the effectiveness of the project's approaches
- CHow the project has progressed against its plans
- DThe suitability of the project management team structure
How the community answered
(28 responses)- A11% (3)
- B4% (1)
- C82% (23)
- D4% (1)
Community Discussion
No community discussion yet for this question.