Which of these processes does NOT trigger the Planning (PL) process?
The correct answer is D. Controlling a Stage (CS). See the full explanation below for the reasoning.
Question
Which of these processes does NOT trigger the Planning (PL) process?
Options
- AStarting Up a Project (SU)
- BInitiating a Project (IP)
- CManaging Stage Boundaries (SB)
- DControlling a Stage (CS)
How the community answered
(59 responses)- A3% (2)
- B7% (4)
- C14% (8)
- D76% (45)
Community Discussion