The correct answer is D. Controlling a Stage (CS). See the full explanation below for the reasoning.

Question

Which of these processes does NOT trigger the Planning (PL) process?

Options

  • AStarting Up a Project (SU)
  • BInitiating a Project (IP)
  • CManaging Stage Boundaries (SB)
  • DControlling a Stage (CS)