The correct answer is C. It replaces a Stage Plan or Project Plan. See the full explanation below for the reasoning.

Question

Which of the following is FALSE regarding an Exception Report?

Options

  • AIt describes a forecast deviation of stage or project level tolerance
  • BIt contains recovery options and a recommendation
  • CIt replaces a Stage Plan or Project Plan
  • DIt describes the consequences of the deviation