PR2F · Question #64
Which product would the Project Manager use for gathering Work Package progress information?
The correct answer is C. Checkpoint Report. See the full explanation below for the reasoning.
Question
Which product would the Project Manager use for gathering Work Package progress information?
Options
- AHighlight Report
- BDaily Log
- CCheckpoint Report
- DProduct Status Account
How the community answered
(60 responses)- A3% (2)
- B10% (6)
- C85% (51)
- D2% (1)
Community Discussion
No community discussion yet for this question.