Which of the following is NOT a PRINCE2 Principle?

The correct answer is B. Project manage by process. See the full explanation below for the reasoning.

Question

Which of the following is NOT a PRINCE2 Principle?

Options

  • AContinued business justification
  • BProject manage by process
  • CManage by stages
  • DTailor to suit the project environment

How the community answered

(71 responses)
  • A
    3% (2)
  • B
    79% (56)
  • C
    6% (4)
  • D
    13% (9)