EXIN
PR2F · Question #431
Which of the following is NOT a PRINCE2 Principle?
The correct answer is B. Project manage by process. See the full explanation below for the reasoning.
Question
Which of the following is NOT a PRINCE2 Principle?
Options
- AContinued business justification
- BProject manage by process
- CManage by stages
- DTailor to suit the project environment
How the community answered
(71 responses)- A3% (2)
- B79% (56)
- C6% (4)
- D13% (9)
Community Discussion