Question

In respect of the project's organization structure, one of the seven principles of PRINCE2 is that every project must have which one of the following?

Options

  • ADefined and agreed roles and responsibilities with an organization structure that engages the
  • BPeople allocated to clearly defined management jobs, assigned to them on a one-to-one basis
  • CAs many stakeholders as possible from the customer environment involved in key decisionmaking
  • DStakeholders who are responsible, accountable, consulted and informed throughout every stage