How is the Project Initiation Documentation used during the Closing a Project process?

The correct answer is A. As the basis for comparing the original aim of the project against what was actually achieved. See the full explanation below for the reasoning.

Question

How is the Project Initiation Documentation used during the Closing a Project process?

Options

  • AAs the basis for comparing the original aim of the project against what was actually achieved
  • BProvides the controls for the final stage of the project
  • CUpdated to include relevant lessons from previous projects
  • DProvides the Project Product Description for approval by the Project Board

How the community answered

(62 responses)
  • A
    74% (46)
  • B
    5% (3)
  • C
    6% (4)
  • D
    15% (9)