Identify the missing words in the following sentence. If the Project Manager needs to know the results of a quality review, the [ ? ] will provide a summary together with the date of any follow-up…

The correct answer is D. Quality Register. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence. If the Project Manager needs to know the results of a quality review, the [ ? ] will provide a summary together with the date of any follow-up meeting.

Options

  • AStage Plan
  • BIssue Register
  • CDaily Log
  • DQuality Register

How the community answered

(57 responses)
  • A
    18% (10)
  • B
    4% (2)
  • C
    5% (3)
  • D
    74% (42)