Which product would be updated to show that a decision has been made to accept an offspecification?

The correct answer is C. Issue Report. See the full explanation below for the reasoning.

Question

Which product would be updated to show that a decision has been made to accept an offspecification?

Options

  • AQuality Register
  • BDaily Log
  • CIssue Report
  • DRisk Register

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    4% (1)
  • C
    75% (21)
  • D
    7% (2)