PR2F · Question #304
Who are allowed to raise issues?
The correct answer is B. Anyone with an interest in the project or its outcome. See the full explanation below for the reasoning.
Question
Who are allowed to raise issues?
Options
- AOnly the Project Manager and Team Manager
- BAnyone with an interest in the project or its outcome
- COnly the Change Authority
- DOnly members of the project management team
How the community answered
(24 responses)- A4% (1)
- B71% (17)
- C8% (2)
- D17% (4)