EXIN
PR2F · Question #291
Who carries out checks independent of the project to ensure that the processes are in place for quality planning and control?
The correct answer is C. Quality Assurance. See the full explanation below for the reasoning.
Question
Who carries out checks independent of the project to ensure that the processes are in place for quality planning and control?
Options
- AProject Board
- BProject Assurance
- CQuality Assurance
- DProject Support
How the community answered
(18 responses)- A11% (2)
- C83% (15)
- D6% (1)
Community Discussion