PR2F · Question #290

Once a product has been completed, from whom would the Team Manager get approval for its completion?

The correct answer is B. The authority defined in the product's Product Description. See the full explanation below for the reasoning.

Question

Once a product has been completed, from whom would the Team Manager get approval for its completion?

Options

  • AProject Manager
  • BThe authority defined in the product's Product Description
  • CQuality Assurance as part of their independent audits
  • DThe producer of the product

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    74% (26)
  • C
    14% (5)
  • D
    3% (1)