According to PRINCE2, which of the following is a benefit?

The correct answer is B. The measurable improvement resulting from an outcome. See the full explanation below for the reasoning.

Question

According to PRINCE2, which of the following is a benefit?

Options

  • AAn improved business operation
  • BThe measurable improvement resulting from an outcome
  • CThe tangible or intangible product resulting from a planned activity
  • DThe result of change, normally affecting real-world behaviour and/or circumstances

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    75% (21)
  • C
    7% (2)
  • D
    14% (4)