nerdexam
EXIN

PR2F · Question #248

Which of the following is considered to be an output of a PRINCE2 project?

The correct answer is B. Any tangible or intangible specialist product. See the full explanation below for the reasoning.

Question

Which of the following is considered to be an output of a PRINCE2 project?

Options

  • AA measurable improvement to the business
  • BAny tangible or intangible specialist product
  • CA consequence of doing the project that is perceived as negative by one or more stakeholders
  • DThe result of change, normally affecting real world behaviour

How the community answered

(18 responses)
  • A
    6% (1)
  • B
    72% (13)
  • C
    17% (3)
  • D
    6% (1)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice