The correct answer is C. Team Manage. See the full explanation below for the reasoning.

Question

Which PRINCE2 role has a specific responsibility for planning, monitoring and managing the team's work?

Options

  • ASenior Supplier
  • BProject Support
  • CTeam Manage
  • DProject Manager