PR2F · Question #172
Which PRINCE2 role has a specific responsibility for planning, monitoring and managing the team's work?
The correct answer is C. Team Manage. See the full explanation below for the reasoning.
Question
Which PRINCE2 role has a specific responsibility for planning, monitoring and managing the team's work?
Options
- ASenior Supplier
- BProject Support
- CTeam Manage
- DProject Manager
How the community answered
(21 responses)- A5% (1)
- B14% (3)
- C76% (16)
- D5% (1)