EXIN
PR2F · Question #171
Which PRINCE2 role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?
The correct answer is C. Change Authority. See the full explanation below for the reasoning.
Question
Which PRINCE2 role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?
Options
- ATeam Manager
- BProject Assurance
- CChange Authority
- DProject Manager
How the community answered
(46 responses)- A2% (1)
- B7% (3)
- C80% (37)
- D11% (5)
Community Discussion
No community discussion yet for this question.