If a product is to be changed, what else must also pass through change control?
The correct answer is C. Product Description. See the full explanation below for the reasoning.
Question
If a product is to be changed, what else must also pass through change control?
Options
- AStage Quality Plan
- BProduct Breakdown Structure
- CProduct Description
- DQuality Log
How the community answered
(41 responses)- A15% (6)
- B7% (3)
- C76% (31)
- D2% (1)