Question
Which statement most accurately reflects the reason for an Exception Assessment in PRINCE2TM?
Options
- AFor the Project Manager to present an Exception Plan to the Project Board
- BThe Project Manager delivers a progress report to the Project Board as a confidence boost
- CThe Project Board meets to consider an Exception Report
- DThe Project Manager reviews and revises the Risk Log with those with assurance roles