nerdexam
EXIN

PR2F · Question #161

PR2F Question #161: Real Exam Question with Answer & Explanation

The correct answer is A. For the Project Manager to present an Exception Plan to the Project Board. See the full explanation below for the reasoning.

Question

Which statement most accurately reflects the reason for an Exception Assessment in PRINCE2TM?

Options

  • AFor the Project Manager to present an Exception Plan to the Project Board
  • BThe Project Manager delivers a progress report to the Project Board as a confidence boost
  • CThe Project Board meets to consider an Exception Report
  • DThe Project Manager reviews and revises the Risk Log with those with assurance roles

Community Discussion

No community discussion yet for this question.

Full PR2F Practice