PR2F · Question #147
Which would require the production of an Exception Report?
The correct answer is D. When the current forecasts for the end of the stage deviate beyond the delegated tolerance. See the full explanation below for the reasoning.
Question
Which would require the production of an Exception Report?
Options
- AWhen a Project Issue is received
- BWhen a Project Board member raises a complaint
- CWhen a Request For Change or Off-Specification has been received
- DWhen the current forecasts for the end of the stage deviate beyond the delegated tolerance
How the community answered
(41 responses)- A5% (2)
- B7% (3)
- C12% (5)
- D76% (31)