PR2F · Question #146

In what sequence would the (a) Project Initiation Document, (b) the Project Mandate and (c) the Project Brief appear in a PRINCE2 project?

The correct answer is B. b, c, a. See the full explanation below for the reasoning.

Question

In what sequence would the (a) Project Initiation Document, (b) the Project Mandate and (c) the Project Brief appear in a PRINCE2 project?

Options

  • Aa, b, c
  • Bb, c, a
  • Cc, a, b
  • Dc, b, a

How the community answered

(24 responses)
  • A
    17% (4)
  • B
    75% (18)
  • C
    4% (1)
  • D
    4% (1)