According to PRINCE2, Project Board members would NOT be involved in which of the following?

The correct answer is C. Running of the project on a day-to-day basis. See the full explanation below for the reasoning.

Question

According to PRINCE2, Project Board members would NOT be involved in which of the following?

Options

  • AConfirming project tolerances with corporate or programme management
  • BAuthorizing the start of the project
  • CRunning of the project on a day-to-day basis
  • DCommunications between the project management team and stakeholders external to that team