Which of the following would define the sequence in which the products are to be created and any dependencies between them?

The correct answer is B. Product flow diagram. See the full explanation below for the reasoning.

Question

Which of the following would define the sequence in which the products are to be created and any dependencies between them?

Options

  • AProduct Status Account
  • BProduct flow diagram
  • CProduct breakdown structure
  • DProduct Description

How the community answered

(46 responses)
  • A
    11% (5)
  • B
    80% (37)
  • C
    7% (3)
  • D
    2% (1)