According to PRINCE2, what are issues likely to affect?

The correct answer is B. The project's performance targets. See the full explanation below for the reasoning.

Question

According to PRINCE2, what are issues likely to affect?

Options

  • AThe Project Manager's workload
  • BThe project's performance targets
  • CThe customer/supplier relationship
  • DOnly the Project Plan

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    75% (21)
  • C
    14% (4)
  • D
    4% (1)