Can a baselined management product be changed once it has been approved?
The correct answer is D. Yes, as long as it is agreed with the relevant authority before it takes place. See the full explanation below for the reasoning.
Question
Can a baselined management product be changed once it has been approved?
Options
- ANo, change control is there to prevent changes
- BYes, there is no restriction
- CYes, but only if the users say so
- DYes, as long as it is agreed with the relevant authority before it takes place
How the community answered
(37 responses)- A8% (3)
- B3% (1)
- C5% (2)
- D84% (31)