PMIPMI
PMP · Question #995
PMP Question #995: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #995. The question stem and answer options stay visible for context.
Submitted by deeparc· Apr 18, 2026Process
Question
A customer asks the project manager to complete a project 10 days earlier than planned due to marketing constraints. After discussing this request with the project team, the project manager concludes that this can be achieved if a few activities can be overlapped. Which approach should the project manager take?
Options
- AFast-track the activities based on limitations and dependencies.
- BRelease the minimum viable product (MVP) earlier and enhance it in the next iteration.
- CReview the schedule and perform resource leveling.
- DAdd subject matter experts (SMEs) to perform the project activities in parallel.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Schedule Management#Schedule Compression#Fast-tracking