PMIPMI
PMP · Question #990
PMP Question #990: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #990. The question stem and answer options stay visible for context.
Submitted by ngozi_ng· Apr 18, 2026Process
Question
A new quality report was distributed to stakeholders after the sponsor approved it. A senior manager requests changing the colors and sizes of some of the graphs included in the report. What should the project manager do?
Options
- AReject the change as the report was approved previously.
- BIncorporate the change in a future report.
- CAsk the team to make the manager's requested changes.
- DAdvise the manager to raise a change request.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Control#Integrated Change Control#Stakeholder Management#Project Documentation