PMP · Question #932
PMP Question #932: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #932. The question stem and answer options stay visible for context.
Submitted by tarun92· Apr 18, 2026Process
Question
A team is about to close a deployment and is waiting to receive critical information from the customer. The customer continues to postpone sending information, which is consequently delaying the deployment. What should the project manager have done to prevent the delay?
Options
- ADelegated the task to the product owner
- BAsked the team to use the sample data
- CEngaged the sponsor and sought their support
- DReceived all key information ahead of time
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Dependency Management#Proactive Planning#Information Gathering#Risk Prevention