nerdexam
PMIPMI

PMP · Question #924

PMP Question #924: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #924. The question stem and answer options stay visible for context.

Submitted by lars.no· Apr 18, 2026Process

Question

While preparing an earned value analysis (EVA) for a project sponsor, the project manager provides the following information in the latest project report: Approved work package cost estimates: US$9,500 Contingency reserves: US$500 Management reserves: 10% of contingency reserves Percent complete of the project: 50% Planned percent of the project: 40% Actual cost (AC) of the project: US$4,500 According to the project status, the current budget at completion (BAC) is considered achievable. What value represents the cost performance required for the remaining work to keep the project cost goal within the baseline?

Options

  • A0.91
  • B0.88
  • C0.64
  • D1.25

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management (EVM)#To-Complete Performance Index (TCPI)#Cost Performance#Project Control
Full PMP PracticeBrowse All PMP Questions