PMI
PMP · Question #881
The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration. Which three techniques should the project manag
Sign in or unlock PMP to reveal the answer and full explanation for question #881. The question stem and answer options stay visible for context.
Submitted by kwame.gh· Apr 18, 2026Process
Question
The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration. Which three techniques should the project manager use? (Choose three.)
Options
- AGantt chart that includes milestones and deadlines
- BRolling wave planning and an adaptive approach
- CRelative estimation to determine the task or deliverable sizes
- DIterations and reviews to continuously keep adapting the plan
- EBottom-up estimating based on a work breakdown structure (WBS)
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Planning#Rolling Wave Planning#Relative Estimation#Iterative Development