PMP · Question #872
PMP Question #872: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #872. The question stem and answer options stay visible for context.
Question
An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty. What should the project manager do to mitigate this risk?
Options
- AReview the issue with the project sponsor and ask for more time to complete this requirement.
- BComplete an impact analysis as the scope of the sprint backlog cannot be changed after the
- CInclude the compliance user story in the next sprint as the team is fully occupied with the current
- DRequest the team to add the user story to the current sprint and let them work on it.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.