nerdexam
PMI

PMP · Question #858

Having managed a similar project while working with previous stakeholders, a project team decided to use the same report format they used in the earlier project. However, stakeholders new to the proje

The correct answer is C. Employ Monitor Communications techniques, which may eventually trigger changes to the. To address stakeholders' misunderstanding of project status reports, the project manager should employ Monitor Communications techniques, which can lead to necessary adjustments in the communications management plan.

Submitted by noor.lb· Apr 18, 2026Process

Question

Having managed a similar project while working with previous stakeholders, a project team decided to use the same report format they used in the earlier project. However, stakeholders new to the project are not fully comprehending the status of the project based on the reports that are being circulated. How should the project manager address this concern moving forward?

Options

  • AAdd the issue to the issue log and determine the corrective action.
  • BCreate a fishbone diagram to determine the root cause for the misunderstanding.
  • CEmploy Monitor Communications techniques, which may eventually trigger changes to the
  • DShare the communications management plan and remind all stakeholders of the agreed-upon

How the community answered

(52 responses)
  • A
    8% (4)
  • B
    2% (1)
  • C
    77% (40)
  • D
    13% (7)

Why each option

To address stakeholders' misunderstanding of project status reports, the project manager should employ Monitor Communications techniques, which can lead to necessary adjustments in the communications management plan.

AAdd the issue to the issue log and determine the corrective action.

Adding to an issue log and determining corrective action is too reactive and does not capture the comprehensive process of monitoring and adapting communication strategies.

BCreate a fishbone diagram to determine the root cause for the misunderstanding.

A fishbone diagram is typically for root cause analysis of *problems* or defects, whereas this situation is a communication mismatch requiring process adjustment rather than a deep technical root cause analysis.

CEmploy Monitor Communications techniques, which may eventually trigger changes to theCorrect

The core issue is that current communications are not effectively reaching and being understood by the new stakeholders, indicating a need for communication effectiveness evaluation. 'Monitor Communications' is the process of ensuring optimal information flow and includes assessing communication methods and formats, which, if found deficient, triggers change requests to the communications management plan to tailor reports to new stakeholders' needs.

DShare the communications management plan and remind all stakeholders of the agreed-upon

Sharing the existing communications management plan would not help if the *plan itself* or its implementation with the current reports is failing to meet the new stakeholders' needs.

Concept tested: Project communications management (Monitor Communications)

Topics

#Communications Management#Monitor Communications#Stakeholder Engagement#Project Reporting

Community Discussion

8
Yusuf A.Yusuf A.Jan 30, 2026

C is correct. One of the senior PMs at my company ran into this exact thing and told me the key is you have to actually Monitor Communications first to see what is and is not working before you go changing the plan, which is why C beats jumping straight to corrective action or root cause analysis.

26
Brenda K.Brenda K.Jan 31, 2026

Right call on C but watch your time here because this one is a 30-second gimme if you just spot the keyword in the stem, not a sit-and-stew question, so answer it and move on.

0
Zlatan X.Zlatan X.Feb 3, 2026

I first leaned toward A because a misunderstanding feels like an issue worth logging, but the real mechanism here is Monitor Communications, which is the process that actually detects gaps in stakeholder comprehension and can trigger corrective changes to how information is delivered.

5
Brenda K.Brenda K.Feb 7, 2026

C is the right call but man that option cuts off mid-sentence, which is annoying under the clock. A is the trap because adding it to the issue log feels proactive, but you are already in Monitor Communications anyway, so flag A and move on.

5
Samuel O.Samuel O.Feb 8, 2026

Spot on on the trap, but the cutoff is exactly why you flag C and keep moving, because in the real world a half-finished comms update gets you the same blank stare from stakeholders that it does on the exam.

0
Grace U.Grace U.Jan 22, 2026

C is right. Does Monitor Communications always mean updating the plan itself?

0
Brenda K.Brenda K.Jan 24, 2026

C is right, and no, Monitor Communications is more about comparing actual comms against the plan and recommending fixes, so only update the plan itself if you find a real gap that needs closing.

0
Samuel O.Samuel O.Feb 16, 2026

Had this on my exam last week, C is right because Monitor Communications drives corrective changes.

0
Full PMP Practice