nerdexam
PMIPMI

PMP · Question #855

PMP Question #855: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #855. The question stem and answer options stay visible for context.

Submitted by tom_us· Apr 18, 2026Process

Question

A team has been working for two months and has consistently missed planned user stories. How should the project manager address this issue?

Options

  • AEnsure the sprint size is appropriate for the iteration duration.
  • BEngage is recruiting a highly skilled resource to reinforce the skills.
  • CPromote changing the iteration duration in order to commit as planned.
  • DConsider using a reward system to encourage timely delivery.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Planning#Sprint Management#Capacity Planning#Scope Management (Agile)
Full PMP PracticeBrowse All PMP Questions